POOL CONSTRUCTION UPDATES 2018 - Pool is completed and ready for opening on May 25, 2019 at 11:00 AM
Work continues on schedule for the new pool. The main drains will be installed this week (weather permitting) and the forms are being constructed for the walls of the pool.
Demolition of old pool began on 4/18 to make way for the new Woodland Springs Pool!!!!!
May 22 the floor for the new pool was poured. The new floor is 12 inches thick!!! Sidewall forms are going up, the rebar is being hand tied together this week. The sidewalls should be poured in the next two weeks, weather permitting. So far, everything is on schedule!!!
The wading pool is gone!!!
The yellow caution tape marks the roof of the pool chemical room. excavating around the room will be "delicate" work in the days ahead so as not to damage the existing walls.
beginning to install the rebar for the floor of the new pool
The floor of the new pool - 12 inch thick concrete and steel rebar Poured on 5/22/18
building the forms for the pool sidewalls . . .walls should be poured in the next two weeks - First week of June
Installing Rebar at the far end of the "deep end" of the pool 5/24/18


Pouring the East Retaining Wall between the Clubhouse and the new Pool deck.

Pool Mechanical Room Walls have been reinforced and repaired. Awaiting the application of the waterproof membrane to side walls, then backfilling will take place once that is completed, construction will begin on the wading pool. (Update, Membrane was installed on 7/26.